Lagos State Commissioner for the Environment and Water Resources, Tokunbo Wahab, has visited the Obalende Motor Park redevelopment project.
The visit comes days after Ìkẹjà Record reported visible progress at the site.
In an X post on November 19, 2026, Commissioner Wahab said engineers were making steady progress on the project. He also expressed optimism that the project would be completed within the next six weeks.
During a visit to the site on November 11, Ìkẹjà Record observed that interlocking had been completed across major sections of the under-bridge. Metal fencing had also been installed to separate the McGregor Channel area from the motor park.
The project was handed over to MTN Nigeria on April 15, 2026 with a 21-week completion timeline which expired on September 11, 2026.
The commissioner said logistical challenges had contributed to the project’s delay. ✚