MTN Nigeria has recorded visible progress on the redevelopment of the Obalende under-bridge into a modern bus park.
During a visit to the site on November 11, 2026, Ikeja Record observed that interlocking had been completed across major sections of the under-bridge. A metal fence has also been installed to separate the McGregor Channel area from the motor park section.
However, some sections of the under-bridge are yet to be interlocked. A Lagos Waste Management Authority (LAWMA) truck was also stationed under the bridge to remove refuse from the McGregor Channel area.
An engineer working on the project told Ikeja Record that construction was initially expected to be completed in November. However, the engineer said the new completion target is December. The delay was attributed to unforeseen circumstances.
Recall that the Lagos State Ministry of the Environment and Water Resources handed over the project to MTN Nigeria on April 15, 2026. The redevelopment was given a 21-week completion timeline. The deadline was September 11, 2026.
Ikeja Record had earlier reported that construction was behind schedule. During a visit on September 14, little visible progress was observed at the site.
Following the report, work resumed at the location. During another visit on October 12, Ikeja Record observed foundation works and the delivery of construction materials.
The redevelopment plan includes an organised transport park, more than 60 public toilet fixtures, kiosks and a recycling drop-off station. It also includes a LAWMA road camp for sweepers and security agencies.
With interlocking and fencing works now underway, the project has recorded considerable progress. However, it remains to be seen whether the revised December completion target will be met. ✚